• About
  • Advertise
  • Careers
Thursday, November 5, 2026
Maritime Gateway
Advertisement
  • Home
  • Shipping
    • NVOCC
    • Tankers
  • Cargo
    • Air Cargo
    • Container Cargo
    • Dry Bulk
    • Liquid Bulk
    • LNG
    • Project Cargo
  • Global News
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle East
  • Ports & Terminals
    • Bulk Ports
    • Container Terminals
    • Port & Terminal Equipment
  • Logistics
    • Freight Forwarding
    • Logistics Parks
    • Supply Chain
    • Warehousing
  • Transport & Multimodal
    • Multimodal Transport
    • Rail
    • Trucking
    • Inland Waterways
  • Insights
    • Magazines
    • Interviews
    • Reports
    • Newsletters
    • Webinars
No Result
View All Result
  • Home
  • Shipping
    • NVOCC
    • Tankers
  • Cargo
    • Air Cargo
    • Container Cargo
    • Dry Bulk
    • Liquid Bulk
    • LNG
    • Project Cargo
  • Global News
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle East
  • Ports & Terminals
    • Bulk Ports
    • Container Terminals
    • Port & Terminal Equipment
  • Logistics
    • Freight Forwarding
    • Logistics Parks
    • Supply Chain
    • Warehousing
  • Transport & Multimodal
    • Multimodal Transport
    • Rail
    • Trucking
    • Inland Waterways
  • Insights
    • Magazines
    • Interviews
    • Reports
    • Newsletters
    • Webinars
No Result
View All Result
Maritime Gateway
No Result
View All Result
Home
Trade, Policy & Economy
Government
Maritime & Shipping Economy

Chattogram Set for Connectivity Boost as Three Mega Projects Near Completion by December

by Maritime Gateway
September 4, 2026
in Maritime & Shipping Economy, Transport & Multimodal
Reading Time: 3 mins read
A A
Chattogram Set for Connectivity Boost

Three long-delayed infrastructure projects in Chattogram are on track to fully open to traffic in December, in a move expected to improve connectivity, ease congestion and cut travel time and costs across Bangladesh’s premier port city. The 15.2-kilometre Wasim Akram Elevated Expressway, the 8.55-kilometre Kalurghat-Chaktai Road-cum-Embankment, and a modern junction at the mouth of the Karnaphuli Tunnel have reached 95 percent, 93 percent and 95 percent progress respectively, at a combined estimated cost of around Tk7,490 crore.

What does the elevated expressway deliver?

Nearly nine years after construction began, the Wasim Akram Elevated Expressway is nearing completion after repeatedly missing deadlines, with delays attributed to land acquisition problems, ramp construction obstructions, and fund disbursement disruptions during the interim government period. The project missed its December 2025 deadline and has been extended to December 2026.

The expressway is designed to improve connectivity between Chattogram city and south Chattogram, cutting travel time to Chattogram Port, Shah Amanat International Airport and the EPZs. It has already reduced travel time between the city centre and the airport to around 20 minutes from roughly ninety minutes. According to Chattogram Development Authority (CDA) Project Director and Executive Engineer Mahfuzur Rahman, ramps at Nimtala, Fakirhat, CEPZ, Wasa and Tigerpass are almost complete, with work on the remaining ramps at Agrabad and Karnaphuli EPZ under way and expected to finish by November, alongside ten toll booths at three points.

The four-lane, 16.5-metre-wide project was approved by ECNEC in July 2017 at an initial cost of Tk3,250 crore, later revised to around Tk4,300 crore. It currently carries about 10,000 vehicles a day, generating Tk6.5-7 lakh in toll revenue; once fully opened, traffic is projected to rise to around 20,000 vehicles daily with toll revenue of Tk14-15 lakh. The government is estimated to be losing around Tk10 lakh a day in toll revenue due to the incomplete ramps.

What does the Kalurghat-Chaktai road add?

The 8.55-kilometre road-cum-embankment from Kalurghat Bridge to Chaktai Khal has reached 93 percent completion, with roughly 250 metres of work remaining at both ends, including sections in the AK Khan and Noman College areas. Twelve sluice gates and associated pump houses at canal mouths have already been completed. CDA Project Director and Executive Engineer Rajib Das said the project, initiated in 2017, was severely affected by the Covid-19 pandemic and a two-year disruption in fund disbursement that lasted until June 2025, though the authority is working to connect both ends and open the road by December despite its latest deadline having expired in June.

Once complete, the road will connect the Dhaka-Chattogram and Chattogram-Cox’s Bazar highways via the City By-pass Loop Road and Quaish Road, allowing vehicles from Kaptai, Rangunia, Raozan and Boalkhali to bypass the city centre en route to south Chattogram, while also protecting key business areas from chronic waterlogging. Its cost was revised from an initial Tk2,275 crore to Tk2,779 crore.

RelatedPosts

GRSE–ONGC Vessel Contract Advances Four-Ship Hybrid Offshore Programme

Energy In Motion Electric Truck Plant Opens in Pune with ₹500-Crore Investment

Cochin Port AI Immigration Pilot Plans Walk-Through Clearance for Cruise Travellers

JSW Infrastructure’s Navkar Wins ₹48 Crore Gati Shakti Cargo Terminal Near Tiruppur

What problem does the Karnaphuli Tunnel junction solve?

The modern junction at the mouth of the Karnaphuli Tunnel has reached 95 percent completion after several deadline extensions, with the deadline now set for December. The CDA undertook the project in 2023, as an extension of the Chattogram City Outer Ring Road Construction Project, after experts criticised the original traffic management design at the tunnel entrance.

Despite completion of the Karnaphuli Tunnel, the 17-kilometre Outer Ring Road from Faujdarhat to Patenga, and the elevated expressway, congestion at the tunnel entrance had remained a major concern, with traffic from the tunnel, airport road, Old Kathgarh Road, the elevated expressway and the Outer Ring Road converging at a single point, particularly during weekend and holiday traffic to Patenga Sea Beach. Rajib, also the junction project’s deputy director, said work on four spans at the Patenga and Ring Road ends was progressing, with traffic movement through the intersection set to open in December.

The Outer Ring Road project, launched in 2013 with an initial allocation of Tk856 crore, has since been revised to a total cost of Tk3,324 crore, including Tk411 crore for the tunnel junction and the CEPZ connecting road.

Tags: BangladeshChattogramInfrastructure projectsKarnaphuli TunnelPort connectivity
Previous Post

VOC Port Floats RFP for Feasibility Study on 2,500-Acre Greenfield Shipbuilding Cluster

Next Post

Port of Antwerp-Bruges strengthens trade relations with India during visit by Prime Minister De Wever

Maritime Gateway

The Maritime Gateway Editorial Team delivers trusted news, analysis, and insights on shipping, ports, logistics, supply chains, and global trade, backed by industry expertise and editorial review.

Next Post
Port of Antwerp strengthens trade relations with India

Port of Antwerp-Bruges strengthens trade relations with India during visit by Prime Minister De Wever

Follow Maritime gateway

    Popular News

    New post style guide

    New post style guide

    October 27, 2026
    Paradip Port Targets 170 MMT Cargo

    Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

    October 16, 2026
    Haryana CM flags off first goods train

    Haryana CM flags off first goods train from rail yard at Integrated Multi Modal Logistics Hub in Mahendragarh district

    August 24, 2026
    Hooghly Cochin Shipyard Wins Repeat Order for Two Luxury River Cruise Vessels

    Hooghly Cochin Shipyard Wins Repeat Order for Two Luxury River Cruise Vessels from Antara

    October 10, 2026

    Business

    No Content Available

    recent

    New post style guide

    New post style guide

    October 27, 2026
    Paradip Port Targets 170 MMT Cargo

    Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

    October 16, 2026
    Edgistify Adds 68,000 Sq Ft Warehouse

    Edgistify Adds 68,000 Sq Ft Warehouse at IndoSpace Luhari to Expand Gurugram Network

    October 16, 2026
    National Strategic Trade Command Centre Opens

    National Strategic Trade Command Centre Opens to Strengthen India’s Export Oversight

    October 16, 2026
    India’s Merchandise Exports Rise 23%

    India’s Merchandise Exports Rise 23% as First-Half Earnings Reach $259.89 Billion

    October 16, 2026

    Latest Shipping and logistics news covering marine, Ports, Shipping, Logistics, containers, dry bulk & tankers that drive South Asian maritime Industry.

    Site Links

    • Interviews
    • News
    • Government
    • Shipping
    • Cargo News

    Site Links

    • Interviews
    • News
    • Government
    • Shipping
    • Cargo News

    Follow Us

    © 2026 – Powered by .

    • Terms of Use
    • Privacy Policy
    • Manage Cookies
    • License
    No Result
    View All Result
    • Home

    © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.