• About
  • Advertise
  • Careers
Tuesday, November 17, 2026
Maritime Gateway
Advertisement
  • Home
  • Shipping
    • NVOCC
    • Tankers
  • Cargo
    • Air Cargo
    • Container Cargo
    • Dry Bulk
    • Liquid Bulk
    • LNG
    • Project Cargo
  • Global News
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle East
  • Ports & Terminals
    • Bulk Ports
    • Container Terminals
    • Port & Terminal Equipment
  • Logistics
    • Freight Forwarding
    • Logistics Parks
    • Supply Chain
    • Warehousing
  • Transport & Multimodal
    • Multimodal Transport
    • Rail
    • Trucking
    • Inland Waterways
  • Insights
    • Magazines
    • Interviews
    • Reports
    • Newsletters
    • Webinars
No Result
View All Result
  • Home
  • Shipping
    • NVOCC
    • Tankers
  • Cargo
    • Air Cargo
    • Container Cargo
    • Dry Bulk
    • Liquid Bulk
    • LNG
    • Project Cargo
  • Global News
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle East
  • Ports & Terminals
    • Bulk Ports
    • Container Terminals
    • Port & Terminal Equipment
  • Logistics
    • Freight Forwarding
    • Logistics Parks
    • Supply Chain
    • Warehousing
  • Transport & Multimodal
    • Multimodal Transport
    • Rail
    • Trucking
    • Inland Waterways
  • Insights
    • Magazines
    • Interviews
    • Reports
    • Newsletters
    • Webinars
No Result
View All Result
Maritime Gateway
No Result
View All Result
Home
News

Land price dispute delays Bay Terminal

by Kalpana Pandey
July 13, 2023
in News, Asia, Ports & Terminals
Reading Time: 2 mins read
A A
Chittagong Port to have bay container terminal.jpeg e1501140833317

The district administration was scheduled to hand over the land at a token. According to CPA sources, the district administration of Chattogram fixed the prices of 500 acres of khas land at Tk 1,241 crore.

The Chattogram district administration in a letter informed the CPA management about the changed decision to chare price for the khas land in May. The CPA, however, appealed to the Ministry of Land to hand over the land at token price.

Earlier, the Chattogram district administration had demanded Tk 3,600 crore for the land.  CPA sources said that the proposal of the Chattogram district administration had been sent to the Land Ministry in January 2022.

A high level meeting held at Shipping Ministry chaired by  ministry Secretary Muhammad Mustafa Kamal on December 27, 2022, directed  Chattogram district administration to hand over the land to the Ministry of land within one month at token price. The district administrations re-fixed the land price at Tk 1,241 crore, six months later in May. But the CPA again appealed to the Ministry of Land to hand over the land at token price. The dispute over land price remained unresolved causing the delay in construction of the Bay Terminal.

Out of 500 acres of land, over 100 acres belong to private owners and  203 acres are owned by the Forest Department.

So, the meeting decided to hand over 500 acres of khas land to CPA at a nominal price. CPA sources also said that the Land Minstry had directed the DC to hand over the land to the Shipping Ministry in June 2021 at a nominal price.

RelatedPosts

New post style guide

Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

Edgistify Adds 68,000 Sq Ft Warehouse at IndoSpace Luhari to Expand Gurugram Network

National Strategic Trade Command Centre Opens to Strengthen India’s Export Oversight

But, Chattogram DC asked the CPA to pay Tk 3,600 crore, the full price of the land in question.

In 2013, the CPA had taken the project of construction of three terminals, a 1,500-metre multipurpose terminal, a 1,225-metre container terminal and a 830-metre container terminal.

A German consultancy firm will conduct a feasibility study and detaile drawings and designs and will supervise the construction. Most of the land would be reclaimed from the sea with mud filling.

Under the project, deep navigational Channel would be dug to facilitate berthing vessels with over 14 metre draft. CPA sources said, the World Bank is now interested to finance the both Break water reclamation of land and the Navigational channel. The cost of the Bay Terminal has been estimated at around Tk 4,000 crore. It is expected that the feasibility study and appointment of contractor would be completed in 2023.

Implementation of the project is likely to begin in 2024 for completion  in 2027.

Tags: Bay Terminalchittagong Port
Previous Post

Evergreen to overtake Hapag-Lloyd as it orders 24 dual fuelled ships

Next Post

Government to consider extending Gelephu dry port

Kalpana Pandey

The Maritime Gateway Editorial Team delivers trusted news, analysis, and insights on shipping, ports, logistics, supply chains, and global trade, backed by industry expertise and editorial review.

Next Post
Nepal-China trade going through a rough patch

Government to consider extending Gelephu dry port

Follow Maritime gateway

    Popular News

    New post style guide

    New post style guide

    October 27, 2026
    Paradip Port Targets 170 MMT Cargo

    Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

    October 16, 2026
    Haryana CM flags off first goods train

    Haryana CM flags off first goods train from rail yard at Integrated Multi Modal Logistics Hub in Mahendragarh district

    August 24, 2026
    Hooghly Cochin Shipyard Wins Repeat Order for Two Luxury River Cruise Vessels

    Hooghly Cochin Shipyard Wins Repeat Order for Two Luxury River Cruise Vessels from Antara

    October 10, 2026

    Business

    No Content Available

    recent

    New post style guide

    New post style guide

    October 27, 2026
    Paradip Port Targets 170 MMT Cargo

    Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

    October 16, 2026
    Edgistify Adds 68,000 Sq Ft Warehouse

    Edgistify Adds 68,000 Sq Ft Warehouse at IndoSpace Luhari to Expand Gurugram Network

    October 16, 2026
    National Strategic Trade Command Centre Opens

    National Strategic Trade Command Centre Opens to Strengthen India’s Export Oversight

    October 16, 2026
    India’s Merchandise Exports Rise 23%

    India’s Merchandise Exports Rise 23% as First-Half Earnings Reach $259.89 Billion

    October 16, 2026

    Latest Shipping and logistics news covering marine, Ports, Shipping, Logistics, containers, dry bulk & tankers that drive South Asian maritime Industry.

    Site Links

    • Interviews
    • News
    • Government
    • Shipping
    • Cargo News

    Site Links

    • Interviews
    • News
    • Government
    • Shipping
    • Cargo News

    Follow Us

    © 2026 – Powered by .

    • Terms of Use
    • Privacy Policy
    • Manage Cookies
    • License
    No Result
    View All Result
    • Home

    © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.