• About
  • Advertise
  • Careers
Tuesday, November 24, 2026
Maritime Gateway
Advertisement
  • Home
  • Shipping
    • NVOCC
    • Tankers
  • Cargo
    • Air Cargo
    • Container Cargo
    • Dry Bulk
    • Liquid Bulk
    • LNG
    • Project Cargo
  • Global News
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle East
  • Ports & Terminals
    • Bulk Ports
    • Container Terminals
    • Port & Terminal Equipment
  • Logistics
    • Freight Forwarding
    • Logistics Parks
    • Supply Chain
    • Warehousing
  • Transport & Multimodal
    • Multimodal Transport
    • Rail
    • Trucking
    • Inland Waterways
  • Insights
    • Magazines
    • Interviews
    • Reports
    • Newsletters
    • Webinars
No Result
View All Result
  • Home
  • Shipping
    • NVOCC
    • Tankers
  • Cargo
    • Air Cargo
    • Container Cargo
    • Dry Bulk
    • Liquid Bulk
    • LNG
    • Project Cargo
  • Global News
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle East
  • Ports & Terminals
    • Bulk Ports
    • Container Terminals
    • Port & Terminal Equipment
  • Logistics
    • Freight Forwarding
    • Logistics Parks
    • Supply Chain
    • Warehousing
  • Transport & Multimodal
    • Multimodal Transport
    • Rail
    • Trucking
    • Inland Waterways
  • Insights
    • Magazines
    • Interviews
    • Reports
    • Newsletters
    • Webinars
No Result
View All Result
Maritime Gateway
No Result
View All Result
Home
News

Port Operation Building ready at Vizhinjam

by Maritimegateway
August 3, 2020
in News
Reading Time: 2 mins read
A A
Vizhinjam Port

August 3, 2020: The Port Operation Building, the nerve centre of the operations of the upcoming international multipurpose deepwater seaport at Vizhinjam, near here, is ready for inauguration.

The four-storey building set up near the breakwater with a floor area of 2,300 sq m will be the first facility to be commissioned at the seaport in Phase I of the PPP project by Adani Vizhinjam Ports Private Ltd. (AVPPL), the multi-port operator executing the project.

 “The plan is to commission the Port Operation Building in August,” a top AVPPL official told The Hindu. All managerial staff, along with critical port control systems like marine control, tower control, port control, and security control will be operating from this building which also has a viewing gallery.

The ground floor will house the reception, health centre, trouble kiosk, restroom, kitchen/ pantry, workstations, manager’s cubicle, and electrical room. Six cabins, managers’ cubicles, workstations, modern conference room, and a documentation room are on the first floor of the building.

Tower control, marine control, QC, operation and security control room, and the viewing gallery are provided on the second floor. Cabins of CEO, Port head, Marine head, Pilot rest room, and board room are on the third floor.

Missed deadlines

The commissioning of the Port Operation Building is as per the revised timeline of the AVPPL that has missed the December 2019 deadline specified in the concession pact inked with the State government to commission Phase I in 1,460 days.

AVPPL was also not able to meet the 1,000-day target of September 1, 2018, announced by Adani Group chairman Gautam S. Adani while inking the pact, owing to a host of reasons, including the Ockhi cyclone and non-availability of granite for the 3.1-km breakwater.

RelatedPosts

New post style guide

Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

Edgistify Adds 68,000 Sq Ft Warehouse at IndoSpace Luhari to Expand Gurugram Network

National Strategic Trade Command Centre Opens to Strengthen India’s Export Oversight

Source: The Hindu

Previous Post

Deep seaport at Matarbari

Next Post

DP World outperforms the market

Maritimegateway

The Maritime Gateway Editorial Team delivers trusted news, analysis, and insights on shipping, ports, logistics, supply chains, and global trade, backed by industry expertise and editorial review.

Next Post
DP World reports 3.2% volume growth in 2016

DP World outperforms the market

Follow Maritime gateway

    Popular News

    New post style guide

    New post style guide

    October 27, 2026
    Paradip Port Targets 170 MMT Cargo

    Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

    October 16, 2026

    Dirty fuels stage a comeback as emissions targets loom

    June 3, 2021
    Paradip Port Cargo Handling Push Targets Over 170 Million Tonnes in FY27

    Paradip Port Cargo Handling Push Targets Over 170 Million Tonnes in FY27

    October 16, 2026

    Business

    No Content Available

    recent

    New post style guide

    New post style guide

    October 27, 2026
    Paradip Port Targets 170 MMT Cargo

    Paradip Port Targets 170 MMT Cargo as PPA Reviews Infrastructure and Operational Efficiency

    October 16, 2026
    Edgistify Adds 68,000 Sq Ft Warehouse

    Edgistify Adds 68,000 Sq Ft Warehouse at IndoSpace Luhari to Expand Gurugram Network

    October 16, 2026
    National Strategic Trade Command Centre Opens

    National Strategic Trade Command Centre Opens to Strengthen India’s Export Oversight

    October 16, 2026
    India’s Merchandise Exports Rise 23%

    India’s Merchandise Exports Rise 23% as First-Half Earnings Reach $259.89 Billion

    October 16, 2026

    Latest Shipping and logistics news covering marine, Ports, Shipping, Logistics, containers, dry bulk & tankers that drive South Asian maritime Industry.

    Site Links

    • Interviews
    • News
    • Government
    • Shipping
    • Cargo News

    Site Links

    • Interviews
    • News
    • Government
    • Shipping
    • Cargo News

    Follow Us

    © 2026 – Powered by .

    • Terms of Use
    • Privacy Policy
    • Manage Cookies
    • License
    No Result
    View All Result
    • Home

    © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.